Coordinate the forming fabric change at the October shutdown
You are the Acting Shift Supervisor coordinating a paper machine clothing change.
What has happened
The forming fabric on the paper machine is showing edge wear at the drive side and its change is locked into the 36-hour October shutdown starting 17 October. The new fabric is on site and its serial number must be confirmed. The change must be completed inside ten hours because a press roll change and a dryer hood inspection follow it. The crane and lifting gear need current inspection tags, section drives, showers, stock and vacuum must be isolated and locked, and the dryer hood inspection needs a confined space permit. The crew includes two operators who have never done a fabric change. The Paper Machine Shift Supervisor has asked you to coordinate the whole task.
Deliverables
- Isolation, permit and inspection checklist
- Updated work order WO-26-3290
- Job safety analysis
- Permit to Work Register entries
- Toolbox Talk Record, task sequence and Production Shift Log record
Documents to use
- Paper Machine Clothing Change Procedure Procedure
- Permit to Work and Isolation Policy Policy
- Permit to Work Form Form
- Toolbox Talk Record Template Template
Systems to use
Permit to Work Register
The register of every permit raised for hot work, confined space entry, heights, containment breaks and electrical work, with isolations and status.
Production Shift Log
The shift record for each production area covering tonnes made, downtime, quality results, plant status and handover notes.
Maintenance Work Orders
The record of preventative and breakdown maintenance requests, their priority, planning and completion across the mill.
Units of competency
Current on training.gov.au for the Pulp and Paper Manufacturing Industry Training Package as at 10 September 2026.
PPMPRV301Co-ordinate and direct clothing changesPPMDEO301Perform dry end operationsPPMWEO201Monitor and control wet end operationsPPMWHS402Identify, assess and control work health and safety risk in own workPPMPRM201Undertake operator level preventative maintenanceQualifications
PPM30121Certificate III in Pulp and Paper OperationsPPM40121Certificate IV in Pulp and Paper OperationsWhat to look for
Evidence guide
Look for isolations that cover every energy source named in the procedure, a job safety analysis with real controls for suspended loads and cutting, permits that list locks for each entrant, and a task sequence that is achievable inside ten hours. The toolbox talk must give the inexperienced operators defined roles. The return to service checks must precede isolation removal.